Lower Mystic Study Area
Project Milestones:
- September 2016 ? November 2016: Assessment of currently planned growth through 2040
- September 2016 ? August 2017: Studying transportation infrastructure and policy options
- October 2016 ? January 2017: Soliciting first round of public input
- October 2016 ? November 2016: Gather public input viaelectronic survey
- November 2016: Kick-offpublic meeting
- November 2016 ? March 2017: Outreach to targeted stakeholder groups
- November 2016 ? January 2017: Testing alternative land use scenario
- April ? September 2017: Research options for financing mechanisms
- September 2017: Public workshop to gather feedback on options
- October 2017: Testing second alternative land use scenario
- October ? December 2017: Testing preferred options and forming conclusions/recommendations
- November 2017 ? January 2018: Drafting recommendations
- January 2018: Presenting study conclusions